Construction to begin September
Work will soon begin on the new roundabout at the intersection of Brecon Road and Regan Street.
We have contracted Fulton Hogan to carry out the construction work and this is due to begin on 1 September 2025.
The work will be completed in stages:
1. Construct the new central island on Regan Street and kerbing at the intersection. This is expected to take at least 5 weeks.
2. From mid-October, pre-reseal repairs will be carried out on Regan Street from the Brecon Road intersection to Hamlet Street.
3. Once Regan Street is resealed in early November (weather dependent), the small roundabout will be installed at the Brecon/Regan intersection
To complete this work safely, traffic management plans will be in place at different stages of the work. During any road closures, residents will still have access to their homes. Due to the nature of the work and the site location please expect some small delays travelling through the work site/detours.
Residents within the area will receive a letter with this detail and any important updates on the work will be shared through the Antenno App and further letter drops.
We appreciate your patience throughout this period. If you have any questions, do not hesitate to contact us, or talk to the friendly team on site.
What about the Portia Street courtesy crossing?
We'll provide another update with construction timeframes for the Portia Street safety improvements soon.